18. Investments in associates and jointly controlled entities

Accounting rules

Accounting rules concerning investments in subsidiaries, associates and jointly controlled entities are presented in note entitled Group composition and consolidation rules (note 2). 

The following table shows key financial data concerning associates and jointly controlled entities consolidated using the equity approach:

As at 31 December 2021 Elektrownia
Ostrołęka Sp. z o.o.
Polimex –
Mostostal S.A.
Polska Grupa Górnicza S.A. ElectroMobility Poland S.A. Total
Stake 50.00% 16.40% 7.66%
Current assets 26 136 1 544 255 2 029 214 3 599 605
Non-current assets 65 553 672 343 8 232 241 8 970 137
Total assets 91 689 2 216 598 10 261 455 12 569 742
Current liabilities 573 465 1 155 998 7 752 847 9 482 310
Non-current liabilities 275 695 2 802 195 3 077 890
Total liabilities 573 465 1 431 693 10 555 042 12 560 200
Net assets (481 776) 784 905 (293 587) 9 542
Share in net assets 128 724 128 724
Goodwill 7 080 15 954 52 697 75 731
Impairment of goodwill (7 080) (52 697) (59 777)
Elimination of unrealised gains/losses (6 797) (6 797)
Book value of equity-accounted investments at 31 December 2021 137 881 137 881
Revenue 869 366 2 225 003 7 347 170 10 441 539
Net result 297 267 101 520 (762 084) (363 297)
Elimination of unrealised gains/losses (6 797) (6 797)
Share of profit of associates and jointly controlled entities 17 252 (398) 16 854

The Group made a consolidation adjustment concerning margins on sales in transactions between the Group and Polimex – Mostostal S.A. ElectroMobility Poland S.A. shares were reclassified into the item: Financial assets measured at fair value. A detailed description is presented in note 2. 

In the item: Share of the results of associates and jointly-controlled entities a provision for future investment commitments toward Elektrownia Ostrołęka Sp. z o.o. of PLN 175 707 thousand is presented. 

As at 31 December 2020 Elektrownia
Ostrołęka Sp. z o.o.
Polimex –Mostostal S.A. Polska Grupa Górnicza S.A. ElectroMobility Poland S.A. Total
Stake 50.00% 16.48% 7.66% 25.00%
Current assets 38 172 1 390 029 1 799 476 17 537 3 245 214
Non-current assets 95 229 673 930 9 080 500 39 274 9 888 933
Total assets 133 401 2 063 959 10 879 976 56 811 13 134 147
Current liabilities 912 443 1 175 007 6 568 576 2 901 8 658 927
Non-current liabilities 213 913 2 733 135 17 2 947 065
Total liabilities 912 443 1 388 920 9 301 711 2 918 11 605 992
Net assets (779 042) 675 039 1 578 265 53 893 1 528 155
Share in net assets 111 246 120 895 13 473 245 614
Goodwill 7 080 15 954 52 697 75 731
Impairment of goodwill (7 080) (52 697) (59 777)
Impairment of investments (129 208) (129 208)
Elimination of unrealised gains/losses (7 026) 8 313 1 287
Book value of equity-accounted investments at 31 December 2020 120 174 13 473 133 647
Revenue 32 562 1 500 978 7 271 145 483 8 805 168
Net result (625 208) 94 309 (1 751 246) (3 762) (2 285 907)
Elimination of unrealised gains/losses (7 026) 8 313 1 287
Share of profit of associates and jointly controlled entities 15 683 (125 213) (631) (110 161)
Impairment of investments in jointly controlled entities (129 208) (129 208)

Change in investments in subsidiaries, associates and jointly controlled entities

As at
31 December 2021 31 December 2020
As at 1 January 133 647 373 016
Change in the change in net assets 16 854 (110 161)
Impairment of investments in jointly controlled entities (129 208)
Purchase of investments 848
Sale of investments (393)
Reclassification to financial assets at fair value (13 075)
As at 31 December 137 881 133 647

Implementation of project to build Elektrownia Ostrołęka C

At 31 December 2021, ENEA S.A. held 9 124 821 shares of Elektrownia Ostrołęka Sp. z o.o., with a nominal value of PLN 50 each and total nominal value of PLN 456 241 thousand. 

On 13 February 2020, ENEA S.A. executed an agreement with ENERGA S.A. suspending financing by ENERGA S.A. and ENEA S.A. for the project to build Elektrownia Ostrołęka C. In the agreement, ENEA S.A. and ENERGA S.A. undertook to carry out analyses, especially concerning the project’s technical, technological, economic and organisational parameters and further financing. 

ENERGA S.A. and ENEA S.A. assumed that suspending financing for the project would result in the company having to suspend its contract executed on 12 July 2018 to build Elektrownia Ostrołęka C with capacity of approx. 1000 MW, along with a contract to convert rail infrastructure for Elektrownia Ostrołęka C of 4 October 2019. 

On 14 February 2020, Elektrownia Ostrołęka Sp. z o.o. issued to the General Contractor for the contract to build Elektrownia Ostrołęka C with capacity of approx. 1000 MW of 12 July 2018 a notice to suspend all works related to that contract, effective 14 February 2020. 

As part of the analytical work performed under the agreement, ENEA S.A. and ENERGA S.A. worked on updating business and technical assumptions as well as assumptions concerning the financing structure within the financial model. On ENERGA S.A.’s part, the results of this work were provided to Elektrownia Ostrołęka Sp. z o.o. on 14 May 2020, when the company received calculations concerning the Project’s profitability in the coal fuel variant. These results were used by the company to perform a CGU test. The CGU test carried out at Elektrownia Ostrołęka Sp. z o.o. shows that completing the Project would generate a negative value, meaning that continuing the Project would be unjustified. 

On 19 May 2020, ENEA S.A. received an electronic copy of Resolution no. 39/2020 of the Management Board of Elektrownia Ostrołęka Sp. z o.o. of 19 May 2020 regarding recognition of impairment losses on the book value of the Company’s assets. As a result of an impairment test on non-current assets performed at Elektrownia Ostrołęka Sp. z o.o., which followed an update of business assumptions by Elektrownia Ostrołęka Sp. z o.o. regarding the construction of power plant Ostrołęka C based on coal technology, the Group’s consolidated financial statements for 2019 include ENEA S.A.’s share of the net loss generated by Elektrownia Ostrołęka Sp. z o.o. Given the fact that it was higher than the value of the stake in this company, it was reduced to zero. Also as of 31 December 2021, ENEA S.A.’s stake in Elektrownia Ostrołęka Sp. z o.o. was worth PLN 0. 

On 2 June 2020 the Management Board of ENEA S.A. accepted a final report on analyses conducted in collaboration with ENERGA S.A. regarding the project’s technical, technological, economic, organisational and legal aspects and further financing. Conclusions from these analyses do not justify continuing the project in its existing form, i.e. the construction of a power plant generating electricity in a process of hard coal combustion. This evaluation was driven by the following: 

  • regulatory changes at the EU level and the credit policy of certain financial institutions, which show that there is far greater access to financing for energy projects based on gas than coal; and
  • the acquisition of control over Energa by PKN Orlen S.A., the strategy of which does not include investments in electricity generation based on coal combustion. 

At the same time, technical analysis confirmed the viability of a variant in which the power plant would use gas („Gas Project”) at the current location of the coal-unit being built. As a result of the above, ENEA S.A.’s Management Board decided to continue building a generating asset in Ostrołęka and change the fuel source from coal to gas. 

On 2 June 2020, a three-party agreement was executed between ENEA S.A., ENERGA S.A. and PKN Orlen S.A., spelling out the following key cooperation rules for the Gas Project:

  • subject to the reservations expressed below, continue cooperation between ENEA S.A. and ENERGA S.A. via the existing special-purpose vehicle, i.e. Elektrownia Ostrołęka Sp. z o.o., and settle costs related to the Project between ENEA S.A. and ENERGA S.A., along with settlements with Project contractors, in accordance with the existing rules, 
  • take into account PKN Orlen S.A.’s potential role in the Gas Project as a new shareholder,
  • ENEA S.A.’s participation in the Gas Project as a minority shareholder with an investment cap, as a result of which the Company will not be an entity co-controlling Elektrownia Ostrołęka Sp. z o.o.,
  • subject to the essential corporate approvals, execute a new shareholders agreement regarding the Gas Project that incorporates the aforementioned cooperation rules,
  • undertake activities intended to secure financing for the Gas Project by ENERGA S.A. together with PKN Orlen S.A. 

From 2 June 2020, the parties to this agreement had been holding talks regarding a new investment agreement specifying rules for the further implementation of the Gas Project, including investment by each of the parties. At the same time, ENEA S.A. on its own evaluated the prospect of participating in the project. 

On 22 December 2020, the Supervisory Board of ENEA S.A., at the request of the Management Board of ENEA S.A., expressed consent for the following: 

  • execution of an agreement with ENERGA S.A. and Elektrownia Ostrołęka Sp. z o.o. regarding cooperation on the division of Elektrownia Ostrołęka Sp. z o.o., 
  • execution of an agreement with ENERGA S.A. regarding cooperation on settling the Elektrownia Ostrołęka C construction investment. 

Also signed on that day were: 

  • an agreement between ENEA S.A., ENERGA S.A. and Elektrownia Ostrołęka Sp. z o.o. regarding cooperation on the division of Elektrownia Ostrołęka Sp. z o.o. (Division Agreement), 
  • an agreement between the Company and ENERGA S.A. regarding cooperation on settling the coal unit construction project as part of Project Ostrołęka C (Settlement Agreement, Coal Project). 

In view of the above, ENEA S.A. and the other parties involved in Project Ostrołęka C have agreed that a part of enterprise related to the gas project will be carved out from Project Ostrołęka C (including in accounting and organisational terms). In connection with ENEA S.A.’s withdrawal from its investment in the construction of a gas unit as part of Project Ostrołęka C, from the date of the carve-out investment costs related to settling the gas project will not be borne by ENEA S.A. 

Both of the agreements include a statement by ENEA S.A. on withdrawal from further participation in the Gas Project. The reasons for withdrawing from further investment in the construction of the gas unit are especially related to ENEA Group’s intention to intensify investing activity in the area of renewable energy sources as well as to invest in the conversion of coal-based sources to gas-based across ENEA S.A.’s existing generating assets that are fully owned by ENEA S.A. 

Reaching these agreements also serves to confirm that in light of ENEA S.A.’s withdrawal from the Gas Project the remaining parties will not be seeking any claims from ENEA S.A. based on this decision. 

In accordance with the Division Agreement, Elektrownia Ostrołęka Sp. z o.o. would be divided through a spin-off (in the meaning of the Polish Commercial Companies Code) of the assets and liabilities (rights and obligations) and other elements that comprise the Gas Project. 

The Settlement Agreement is essential to the performance of the Division Agreement, which requires cooperation by the shareholders of Elektrownia Ostrołęka Sp. z o.o., including the settlement of costs related to the Coal Project. In accordance with the Settlement Agreement, costs related to the Coal Project will be settled based on the existing arrangements between the company and ENERGA S.A. and ENEA S.A. 

On 31 December 2020, in accordance with the Settlement Agreement (which amended the loan agreement of 23 December 2019 in this regard), ENEA S.A. bought from ENERGA S.A. half of ENERGA S.A.’s receivables due from Elektrownia Ostrołęka Sp. z o.o. for a price equal to the nominal value of the receivables being sold, i.e. PLN 170 000 thousand, plus interest accrued from 31 December 2020, amounting to PLN 11 617 thousand. 

Impairment of loans issued to Elektrownia Ostrołęka Sp. z o.o. as at 31 December 2021 amounted to PLN 225 610 thousand, together with interest (the value of these loans was written off to zero). 

On 26 February 2021 ENEA S.A. and ENERGA S.A. executed with Elektrownia Ostrołęka Sp. z o.o. Annex 1 to the PLN 340 million loan agreement of 23 December 2019 and Annex 6 to the PLN 58 million loan agreement of 17 July 2019. Pursuant to the provisions of the aforementioned annexes, Elektrownia Ostrołęka Sp. z o.o. undertook to make a one-off loan repayment to ENEA S.A. of PLN 170 million and PLN 29 million, respectively, together with interest, by 30 June 2021. Next, on 30 June 2021, ENEA S.A. and ENERGA S.A. executed with Elektrownia Ostrołęka Sp. z o.o. Annex 2 to the PLN 340 million loan agreement of 23 December 2019 and Annex 7 to the PLN 58 million loan agreement of 17 July 2019. Pursuant to the provisions of the aforementioned annexes, Elektrownia Ostrołęka Sp. z o.o. undertook to make a one-off loan repayment to ENEA S.A. of PLN 170 million and PLN 29 million, respectively, together with interest, by 30 September 2021. On 30 September 2021 ENEA S.A. and ENERGA S.A. executed with Elektrownia Ostrołęka Sp. z o.o. Annex 3 to the PLN 340 million loan agreement of 23 December 2019 and Annex 8 to the PLN 58 million loan agreement of 17 July 2019. Pursuant to the provisions of these annexes, the deadline for the one-off repayment by Elektrownia Ostrołęka Sp. z o.o. of the loans along with interest was prolonged to 29 October 2021. 29 October 2021 ENEA S.A. and ENERGA S.A. executed with Elektrownia Ostrołęka Sp. z o.o. Annex 4 to the PLN 340 million loan agreement of 23 December 2019 and Annex 9 to the PLN 58 million loan agreement of 17 July 2019. Pursuant to the provisions of these annexes, the deadline for the one-off repayment by Elektrownia Ostrołęka Sp. z o.o. of the loans along with interest was extended to 29 April 2022. 

On 25 June 2021, Elektrownia Ostrołęka Sp. z o.o. as vendor and CCGT Ostrołęka Sp. z o.o. as buyer (a wholly-owned subsidiary of ENERGA S.A.) signed a sale agreement and associated agreements regarding an SPV (excluding certain assets) intended (and used as such) to implement economic tasks covering the construction of a gas-fired power generating unit in Ostrołęka and the subsequent operation of this unit (Gas Plant). The business being sold includes generally all of the SPV’s asset and non-asset components in use as of the transaction date in connection with preparations to begin an investment process consisting of the construction of the Gas Plant. The transaction is intended to facilitate the implementation of a gas project by CCGT Ostrołęka Sp. z o.o. as a company that will replace Elektrownia Ostrołęka Sp. z o.o. in implementing the investment in Ostrołęka. The sale price for the business being sold (transaction value) is currently estimated at approx. PLN 166 million. The price is set on a preliminary basis as additional considerations will apply in determining the final price. 

On 25 June 2021, Elektrownia Ostrołęka Sp. z o.o. and CCGT Ostrołęka Sp. z o.o. on the one hand and GE Power sp. z o.o., based in Warsaw, GE Steam Power Systems S.A.S. (former name: ALSTOM Power Systems S.A.S.), based in Boulogne-Billancourt, France (Coal Project Contractor), and General Electric Global Services, GmbH, based in Baden, Switzerland (together with GE Power sp. z o.o. – Gas Project Contractor) on the other hand signed a Contract Change Document concerning the contract of 21 July 2018 to build unit C at Elektrownia Ostrołęka, with a capacity of 1000 MW, and an Agreement on the settlement of the Coal Project. The Contract Change Document is structured in a way that facilitates implementation of the Gas Project by CCGT Ostrołęka Sp. z o.o. as a company that will replace Elektrownia Ostrołęka Sp. z o.o. in implementing the investment in Ostrołęka, which is related, inter alia, to the fact that ENEA S.A. has confirmed its withdrawal from participating in the Gas Project. The agreement concerning the Coal Project settlement regulates the rights and obligations of Elektrownia Ostrołęka Sp. z o.o. and the Coal Project Contractor mainly in connection with the settlement of construction work completed by the Coal Project Contractor until the contract was suspended, maintenance and security activities during Contract suspension and work related to finishing the work dedicated to implementing the Coal Project. Under this agreement, the Coal Project was supposed to be settled by the end of 2021, and the entire amount that Elektrownia Ostrołęka Sp. z o.o. will be obligate to pay to the Coal Project Contractor, taking into account expenditures incurred thus far, will not exceed PLN 1.35 billion (net). 

On 22 December 2021 Elektrownia Ostrołęka Sp. z o.o. executed an annex to this agreement with the Coal Project Contractor. The annex extends the settlement deadline to 25 March 2022 and results from a verified mechanism for settling the Coal Project. The entire amount that Elektrownia Ostrołęka Sp. z o.o. will be obligated to pay to the Coal Project Contractor will not change and will not exceed PLN 1.35 billion (net). 

In connection with these agreements being signed and based on the status of settlements between Elektrownia Ostrołęka Sp. z o.o. and the Coal Project Contractor, a provision for future investment liabilities toward Elektrownia Ostrołęka Sp. z o.o. and ENERGA S.A., initially amounting to PLN 222 200 thousand, was partially released in these consolidated financial statements, with the amount released being PLN 175 707 thousand. This amount was recognised in the consolidated statement of comprehensive income in the item „Share of the results of associates and jointly-controlled entities.” The provision amounted to PLN 46 493 thousand as of 31 December 2021, which is the best possible estimate in connection with uncertainty related to final settlement amounts. 

ENEA S.A.’s commitment to provide funding for Elektrownia Ostrołęka Sp. z o.o. resulting from the existing agreements (especially the agreements dated 28 December 2018 and 30 April 2019 and the Settlement Agreement) that is still outstanding amounts to PLN 620 million. ENEA S.A. does not have sufficient information on any potential additional contributions or their potential deadlines, aside from those above. 

On 31 January 2022 Elektrownia Ostrołęka Sp. z o.o. terminated an agreement implementing the capacity obligation contracted by the company as a result of a capacity market auction for 2023. The agreement was terminated due to the supply source being changed from coal to gas in the project to build and operate a new power plant in Ostrołęka. 